Construction Draw Schedule: How It Works and How to Build One

A construction draw schedule is the agreed plan for releasing money in stages as work is finished and verified. It lists each milestone, the share of the budget that milestone unlocks, the paperwork required and who approves it. A schedule built around objective milestones and a complete paperwork package gets funds released faster and keeps the job from stalling for lack of cash. At Axenia Construction, a licensed, women-owned general contractor in Rockville, MD, we work with owners across Maryland, DC and Northern Virginia, and the owners who have the smoothest builds are the ones who settle this schedule before the first shovel goes in.

Axeniaconstruction
Keep Construction Payments Tied to Progress
Axenia Construction provides residential, commercial, and industrial construction services for owners across Maryland, DC, and Northern Virginia.

Visit

TL;DR

  • A draw schedule says when completed work becomes billable. The project schedule says when work happens. The Schedule of Values says what each part of the contract is worth.
  • Residential builds typically use five to eight draws, each tied to a checkable milestone such as foundation, framing and dry-in, or rough-ins.
  • Each draw usually needs a request, lien waivers, invoices, an inspection and a title check before funds go out, so plan for roughly one to two weeks between request and money.
  • Lenders hold back part of each draw or the final payment (commonly 10%) until the certificate of occupancy and final waivers are in.
  • Agree the milestone definitions, billing calendar and backup documents in writing before work starts.

Table of Contents

What a construction draw schedule actually is

When you finance a build with a construction loan, the lender does not hand over the full amount at closing. It releases funds in installments, called draws, as the work progresses. A construction draw schedule is a financial plan outlining when project funds will be requested or payments released, often based on milestones or percentage of completion.

The same idea applies when no bank is involved. Many owner-contractor contracts divide the contract price into milestone payments, and the contractor bills against those milestones. Either way, the logic is the same: money follows verified work.

For the reader, this matters in practical ways:

  • Homeowners know exactly when large payments are due and what has to be finished first.
  • Commercial property owners and business owners can match cash needs to a tenant improvement or buildout timeline.
  • Realtors advising clients on a build or major renovation can explain why funding arrives in stages rather than all at once.

Draw schedule, project schedule and Schedule of Values: three different documents

People mix these up constantly, and the confusion causes real delays.

The project schedule shows when work happens, while the draw schedule shows when completed work becomes billable. Each draw on the schedule lists the work stage, the payment trigger, the required documentation, the approval step and the recipient.

The Schedule of Values (SOV) is a third document. The draw schedule sets the payment sequence, while the SOV breaks the contract into priced work categories. In plain terms: the SOV answers “what portion of the contract belongs to framing?” and the draw schedule answers “when do we ask for that money?”

If you are a contractor building the SOV that sits underneath your draws, our guide to building an approvable Schedule of Values walks through it step by step. For the billing side once work is underway, see how progress payments work.

A sample residential draw schedule

The most useful way to understand a draw schedule is to read one. A savings and loan association publishes a sample construction disbursement schedule that splits a house build into six disbursements. Rounded to the milestone groupings, it looks like this:

Draw Share of loan Typical milestones
1 20% Lot cleared and filled (3%), pilings, beams and rebar (4%), sub-plumbing (3%), slab poured (10%)
2 20% Framing walls (10%), framing roof (6%), cornice and roof deck (2%), windows (2%)
3 20% Exterior doors, paint prime, plumbing, electrical and HVAC rough-ins, roof complete, insulation
4 15% Brick and siding (5%), sheetrock (5%), walks and drives, cabinets, countertops
5 20% Trim, painting, fixtures, flooring, appliances, site work
6 5% Occupancy permit and final inspection

Notice three things. First, the milestones are physical and checkable: a slab is poured or it is not. Second, the heaviest early draws cover the expensive structural stages. Third, the last 5% waits for the occupancy permit and final inspection, which gives everyone a reason to finish the punch list. The same document notes a $125 re-inspection fee, a reminder that failed inspections cost money as well as time.

Other lenders slice the work a little differently. A typical residential new build runs five to eight draws over a 12 to 24 month build, starting with land payoff and soft costs, then foundation, framing and dry-in, rough-ins, drywall and exterior finish, interior finishes, and final inspections, with a 5 to 10% holdback released at the certificate of occupancy. Interest accrues only on the balance actually drawn.

Concrete foundation at a Maryland home build

A commercial example

Commercial schedules follow the same pattern with different weights. One lender’s typical ground-up multifamily structure is 15% for land and permits, 20% foundation, 25% framing and structure, 20% mechanical, electrical and plumbing rough-in, 15% interior finishing and 5% at certificate of occupancy. Those percentages apply to the construction-draw portion of the loan, not the whole commitment: in the lender’s example, $8.2 million of a $10 million commitment, with the rest set aside for an interest reserve, contingency and fees.

For a tenant buildout, the stages shift again: permits and design, demolition and framing, MEP rough-in, drywall and ceilings, finishes, and closeout. Finishes are the stage owners most often under-budget, so it pays to settle specifications early. A tenant improvement finishes guide on what to specify and budget helps you size the finishes draw before the schedule is locked. If you are planning a space, our tenant buildout timeline shows how the stages stack up in time.

How to build a draw schedule, step by step

Here is the routine we would follow for any project, with the places it commonly goes wrong.

1. Confirm the contract and the lender’s requirements

Start with the contract value, payment terms, retainage percentage and whatever the lender requires. RedTeam’s five-step method begins here for good reason: if the contract says one thing and the loan agreement says another, the draw schedule inherits the conflict. Read both before you draft anything.

2. Build a detailed Schedule of Values

Break the contract into priced line items you can verify on site. For lump sum work, a city engineering bureau describes the SOV as a cost-loaded schedule of activities equal in total to the lump sum bid, and it becomes the basis for each progress payment. Vague lines such as “miscellaneous” invite disputes. Specific lines such as “rough electrical, floors 1 and 2” do not.

3. Spread the money across milestones

Allocate the financial scope to match the timeline, planned milestones and payment terms. The projected payments for upcoming months should equal the remaining contract balance, so the plan and the actual spend stay in step. Two design principles help. Draws should be big enough to fund mobilization and the next phase, but small enough that no one is paying far ahead of the work. And every trigger should be an objective checkpoint, such as an inspection or a pass/fail item like roof dry-in, rather than a squishy label like “halfway done with the interior.”

If your project is phased, for example an occupied building renovated in zones, tie draws to each phase. Our guide to building a construction phasing plan shows how to define those zones.

4. Define each milestone in writing

If a draw is released at framing completion, everyone needs the same definition of framing completion before work begins. Aligning the schedule with the contract, budget, lender requirements and field reality protects contractors, who know what to document, and owners and lenders, who know what to verify.

5. Set the billing calendar and backup documents

Put the cutoff date, pay application due date, review window and payment date in writing with the owner and lender. Then list the backup for every draw: lien waivers, subcontractor invoices, material receipts, photos and certificates of insurance.

6. Get approval before the first draw

Have the Schedule of Values and the draw schedule approved by the owner and lender before the first request. Changing the rules after money is owed is where friction starts.

How a draw moves from request to money

The basic sequence is consistent across lenders. The contractor finishes a defined phase, submits a draw request with documentation such as lien waivers, invoices or a progress report, and the lender orders an inspection before approving and wiring funds. Three parties are involved: the general contractor, who does the work and assembles the package; the lender, who reviews it; and the inspector, who confirms that the physical work matches the request.

The inspection is the control that makes the whole system work. The draw schedule gives the lender control over how and when funds are distributed and a chance to verify completed work before releasing money. Builders commonly submit requests on an AIA Application and Certificate for Payment form, the standard industry billing form.

How long it takes

Timing varies by lender and loan type, so build the delay into your cash plan:

The lesson: an incomplete package restarts the clock. Submit requests ahead of when you need to pay subcontractors and suppliers, not on the day the invoices come due.

Documents, retainage and holdbacks

What goes in a draw package

Requirements differ, but the usual contents are consistent. One bank’s construction guide lists borrower authorization, an updated sworn statement from the builder, lien waivers for previous payments, a site inspection report and a title update confirming no new liens, plus a foundation survey with the first draw only. Larger commercial loans often add AIA G702 and G703 forms, lender-approved change orders, backup invoices and a subcontractor list.

Lien waivers deserve a word. A lien is a legal claim against the property that an unpaid subcontractor or supplier can file. A waiver is their written release of that claim. The standard rhythm is conditional waivers with the current draw and unconditional waivers for the prior draw. Missing waivers are one of the most common reasons a lender pauses funding.

Retainage versus lender holdback

These are two separate things that owners often confuse:

  • Retainage is money the owner withholds from the contractor until the work is substantially complete, most often 10% in the United States.
  • Lender holdback is money the bank retains from each payment under a progress payment plan. Banks normally hold back 10% to 20% of each payment to cover overruns or unpaid supplier and subcontractor bills.

Before final payment, expect a closeout package: a certificate of occupancy or final completion, final lien waivers, the contractor’s final affidavit and a final site inspection and title check. Our construction closeout checklist covers how to assemble it without a paper chase.

Paying interest during the build

During construction you typically pay interest only on the amount drawn, not the full loan. One lender notes payments are generally due by the 1st of each month, and that the home must be 100% complete before the final draw. If you are financing a renovation rather than a new build, our home renovation loan application guide explains the application side.

If you plan to refinance into a permanent mortgage afterward, note that in Fannie Mae’s two-closing process, contractor draw requests are processed per the contract draw schedule, and completion requires an appraisal update, lien waivers and a certificate of occupancy.

Common draw schedule mistakes

  1. Vague milestones. “Framing done” means different things to a contractor and an inspector. Define it before work starts.
  2. Front-loading. Paying far ahead of the work leaves the owner exposed if the project stalls.
  3. Back-loading. Draws too small to fund the next phase starve crews and slow the job.
  4. Incomplete packages. Missing waivers, invoices or insurance certificates reset the review clock.
  5. Ignoring the delay. Submitting on the day bills are due guarantees a cash gap.
  6. Skipping change orders. Scope changes that the lender has not approved can hold up the next draw. Update the schedule when the scope changes.
  7. Forgetting the schedule itself. If the build falls behind, draws slip too. Our guide to fixing construction schedule delays covers how to get back on track.

Where Axenia fits

A draw schedule works best when the contractor, owner and lender share one clear picture of the project. We are a licensed general contractor serving residential, commercial and government clients, and our approach centers on meticulous project management and transparent communication. Our general contracting and design-build services put design, permitting and construction under one roof, and local permitting expertise across Maryland, DC and Northern Virginia helps the milestones on paper match what inspectors expect on site. For commercial spaces, see our tenant buildout service. If you are weighing contractors, our list of questions to ask a contractor before you hire is a good place to start.

Axeniaconstruction

Planning a build, addition or buildout and want the numbers and milestones clear from day one? Talk to our team at Axenia Construction.

Our perspective

Owners tend to see the draw schedule as a lender’s form. We see it as the first honest conversation about a project: what gets built, in what order, and what proof shows it is done.

When a schedule is written around milestones that anyone can verify, the project runs on trust instead of guesswork. The owner knows what each payment buys. The lender sees the work behind each request. The crew knows when the next phase is funded.

That is why we put so much weight on transparent communication and careful project management. As a women-owned firm that builds genuine relationships with the owners we serve, we want you to understand your schedule before you sign it, not after the first request comes back with questions. With design, permitting and construction handled together in a design-build project, the plan you approve at the start is the one that guides the work.

Arienne

FAQ

What is a draw schedule in construction?

It is the agreed plan for releasing money in stages as milestones are completed. Each draw names the work stage, the amount, the documents needed and who approves it. It is different from the project schedule, which shows when the work happens.

How many draws does a typical home build have?

Most single-family builds use five to eight draws, often with a common pattern of foundation, framing and roof dry-in, rough-ins, insulation and drywall, finishes, and final closeout. The exact number and percentages come from your lender and contract.

How long does it take to receive a draw?

Plan on roughly one to two weeks from a complete request. One commercial guide puts a monthly draw at 7 to 14 business days, while residential lenders often move faster. Missing paperwork extends the timeline, so submit early.

Who inspects the work before each draw?

Usually an inspector or construction consultant working for the lender. They confirm that the work in the request is actually in place. Municipal inspections and your own site walkthroughs are separate, but their records often go into the draw package.

What is the difference between retainage and a lender holdback?

Retainage is withheld by the owner from the contractor, most often 10%, until substantial completion. A lender holdback is withheld by the bank from each draw, commonly 10% to 20% under a progress payment plan. Both are released after closeout items such as final waivers and the certificate of occupancy.